Conceptualization and Development of MVP as an ERP application for web & mobile platform
Organization Name: TNT CTSX Technologies
Job Title: Co-Founder
Area: Operations
Industry: IT & Manufacturing
Approach / Methodology: Hybrid
Team Size: 5
Budget: Classified
Start Date: January 2021
End Date: October 2021
Project Objectives
​
The objective was to conceptualize and develop an MVP for a mini ERP solution as a web and mobile application to manage the lifecycle of commercial tires.
Outcome
The result was a mobile and web-based application named "iTRAMS" with limited features, which was tested by the internal team in the field.
​
My Role
My role was as Project Manager.
​
My responsibilities
​
Methodology: Agile
-
Collaborated with the project sponsor to establish the roadmap, goals, vision, and mission.
-
Coordinated with the product owner to gather requirements, and write epics, features, and user stories.
-
Defined the project scope and out-of-scope activities.
-
Identified stakeholders, including customers for the internal testing program.
-
Formed a team of 5 members and adopted the Scrum methodology.
-
Developed the project budget and schedule plan, which was approved by the sponsor.
-
Acted as Scrum Master, coaching the team on Scrum principles and benefits.
-
Created a quality management plan to ensure standards were met during execution.
-
Conducted qualitative and quantitative risk assessments, creating a risk management plan and risk register.
-
Established stakeholder communication and engagement plans.
-
Assigned resources and developed a resource management plan.
-
Implemented a 2-week sprint cycle, conducting daily stand-ups to maintain Scrum adherence.
-
Addressed and resolved team conflicts promptly.
-
Worked with the product owner to prioritize the product backlog regularly.
-
Managed change requests from stakeholders, incorporating them into the subsequent sprints.
-
Participated in sprint planning meetings, ensuring feasible story points for each sprint to maintain velocity.
-
Monitored progress using burn-up and burn-down charts to keep the project within scope, time, and budget.
-
Facilitated sprint retrospectives, implementing improvements in subsequent sprints.
-
Secured sponsor acceptance of deliverables upon project completion.
-
Closed the project by documenting lessons learned, disbanding the team, and archiving project records.
​​
​
​​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​​​​​​Deliverables
-
A roadmap for product development with clearly defined goals, mission, and vision.
-
A prototype cum MVP mobile and web application named "iTRAMS - intelligent Tyre and Retreading Advance Management System" is ready for internal testing with customers.
​
​